I often “Execute Flow” within another flow. Is there a way to force the Called Flow to complete before the Calling Flow continues?
Just to clarify, I "call a subroutine" from a running flow. I do not want the calling process to continue until the called flow has terminated.
Complete Called Flow before continuing calling flow?
Moderator: Martin
Re: Complete Called Flow before continuing calling flow?
Hi,
You can activate option Wait for called flows to finish in action Execute Flows.
Regards,
Martin
You can activate option Wait for called flows to finish in action Execute Flows.
Regards,